Second 1000 MWe Unit at Kudankulam goes critical

By Swati Deshpande,

Added 13 July 2016

Tamil Nadu’s total atomic power capacity to go up to 2,440 MW

Second nuclear power reactor unit of 1,000 MWe capacity at Kudankulam in Tamil Nadu achieved criticality recently. This is the second 1,000 MW pressurised water reactor to go critical in the country. The first unit at Kudankulam went critical in July 2013.

The unit will start commercial generation in four to six months' time. Prior to that, tests have to be conducted and then the unit will be connected to the Southern power grid.

Once the second unit at Kudankulam starts power generation to its full capacity, the total atomic power capacity in Tamil Nadu would go up to 2,440 MW.